Get alerted when tasks have no dependencies set


In my previous blog post "Highlight items after every change", you have learnt how to apply highlight the tasks after every change by using Visual Basic for Applications macro.

Best practice followed when linking tasks is (a) Don’t link summary tasks to summary task – as it complicates the scheduling logic, (b) Every other task should have at least one predecessor or successor task.

It is easy to validate the above provide your plan is small (this is quite relative again 🙂 ). In this blog post, I will walk through on how VBA macros can color tasks automatically with no dependencies set and color summary tasks with dependencies set.

In the above plan, you can notice I have violate the first rule (a) Phase 1 (task id 1) is linked to Phase 2 (task id 4), (b) Go Live (task id 7) is not linked to any other tasks

Let’s start with a pseudocode for this requirement.

1. For each task in plan do
1.1. If task is not empty and active
1.1.1. If the task is summary task
1.1.1.1. If number of dependencies is greater than zero, then mark it.
1.1.2. If the task is not summary task
1.1.2.1. If number of dependencies is zero, then mark it
2. Color the marked task

Now you need to translate each statement by using Project model object, properties and methods.

1. Click View tab. Click Macros dropdown and select Visual Basic
image12.png?w=640

2. In the editor, double click your current project on the left panel.
3. Now change the object and procedure to "Project" and "Calculate".

4. This will include a private sub-routine which will be invoked automatically after calculation!!

5. Within this sub-routine, include the below script

The above sub-routine checks if the current view is Gantt Chart. Then, it changes the text styles of marked tasks (Item:=5) to default color. Then, we loop through the task list and mark the tasks having the issues.

After closing the editor, I just retyped a task information and Project automatically colors the task that need attention in red.

Advertisements

One thought on “Get alerted when tasks have no dependencies set

  1. Pingback: Stop! Don’t delete approved tasks | Voices on Microsoft Project

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s