What are you finishing today?


Project 2013 ships with "Tasks Due This Week" filter. This filter shows detail tasks with finish between the start and end of the current week.

What if you want to display the tasks due today?

1. On the View tab, click the down arrow of the Filter box to display the drop-down menu and then select New Filter in the menu to open the Filter Definition dialog box.
2. Enter the name "Tasks Due Today" and set the filter criteria as it is seen below and click Save:

The value string “Today is:”? evaluates to the Current Date field entered in Project Information dialog box. If we use a different prompt string, for example, "Enter a date:"?, then the filter asks for a date to compare with the task finish dates.

3. On the View tab, select the filter "Tasks Due Today" from Highlight: dropdown (by default "No Highlight" is applied)

So, what are you finishing today?

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s